St. Vincent Fishers Hospital, Fishers, Indiana

PROJECT: St. Vincent Fisher Hospital, Fishers, Indiana
Facility Director – Victor DeTienne
和记app下载 Representative – AB Young Company, Byron Koch

EQUIPMENT:
• Two VMP-50 LE Steam Boiler Skid Mounted with a boiler feed system and blow down separator and Mod Sync Control panel
• SN # 116416-FBW
• 116294-FBW-REV B
和记app下载 • Steam requirement for Surgery Autoclaves and Building Humidification, Dual Fuel fired, 150 psig design, operating pressure 80 psig, Boilers, Knockdown Skidded system.

和记app下载The project presented a challenge due to the fact that St. Vincent required a knockdown steam system in order to get in the existing location, where before they had Two boilers. The hospital determined they needed addition steam capacity. Unfortunately, there was no physical space to get the boilers into the same space as the ICS-20 boilers existed before. Fulton provided the solution with a knock down steam boiler package. In the photos you can see challenge we faced locating the new boilers in an area that housed a building column. We also incorporated (3) Vantage 2000 Condensing boilers with Low Nox capability in this mechanical space.

 

St vincent 2st vincent 1St vincent 3

 

CONSULTING ENGINEER: BSA LifeStructures, Indianapolis, IN, Kevin McNutt, PE
INSTALLING CONTRACTOR: Leach & Russell Mechanical Contractors, Fishers, IN
PROJECT ENGINEER: Andy Smith